Data Centre Phase 3
Project Name
Data Centre Phase 3
Client:
Blue Chip Company
Sector:
Private
Location:
West Dublin
Main Contractor:
John Sisk & Sons
Contract Period:
Feb 2014- Aug 2015
• New Data Facility 21,000m2 building.
 • Reduce level strip and disposal 55,000m3 Greenfield Inert to licensed Tip. Rock breaking 6,000m3 for site prep.
 • Site Prep & Bulk Filling Hardcore.
 • Substructure pad foundations & bulk filling lean mix.Rock breaking 3000m3 for pads.
 • Internal Grading Floors & Perimeter Ground Beams. Internal Drainage &Pop Ups/ Radon system.                                                                                                               • Storm/Foul Drainage deep. 500m deep 900 dia SW drainage associated rock breaking. Deep Petrol Interceptors.
 • Temporary Works.
 • Ducting LV/COMMS/MV Power supply.
 • Watermain/Sprinkler Mains.
 • Sprinkler Tanks & associated pump houses.
 • Connections to local authority services.
 • External Works – Footpaths, Roads, Kerbs, Paving, Paving, Generator Compounds, Yard Slabs.
 • Landscaping – Construction Berms & Topsoil external areas.