DUB 68 / 78
Project Name
DUB 68 / 78
Client:
Confidential
Sector:
Private
Location:
West Dublin
Main Contractor:
PJ Hegarty
Contract Period:
October 2023 To February 2023
- Two new Data Centres with a combined footprint of 50,000m2.
- Site Strip and disposal of Circa 50,000m3 inert material offsite
- Excavation of Substructures consisting of pad and strip foundations (18,000m3)
- Deep line drainage reaching 8.00m depths consisting of 375mm-1200mm diameter pipe lines
- 44 kilometres of ducting to be installed, consisting of MV, LV and Fibre
- Breaking 20,000m3 of rock within trenches and substructures
- Completion of Roads, Paths and Paving around new data centres