Sandyford Central
Project Name
Sandyford Central
Location:
Dubin
Main Contractor:
John Paul Construction
Contract Period:
Ongoing
Site Enabling Works
- Site Setup (installation of temp services to Compound)
- Creation of Additional Site entrances at Carmanhall Road, Blackthorn Drive (Realignment of Kerbs and Dishing of Paths)
- Adjustment to Chamber with Paths
- Demolition and Alteration of Existing Site Hoarding x 305mts (Disposal of Concrete off site)
- Break out concrete footpath at site boundary and hand dig around ESB cables to facilitate disconnection of ESB Substation. Back fill with sand and install stone back to surface level.
- Demolition of Existing ESB Sub Station
- Break Overburden of Rock at Rockbrook for rock Stabilization
- Backfill around existing watermain and install 100mm temp slab, Blackthorn drive entrance gates to site – 5m wide by with of the site
- Remove Blockwork Wall to Carmanhall Road (20mts)
- Demolish Existing Paths left on Site
Pile Attendance
- M&N to Provide Pile Attendance to PJE as required (14t Excavator + 9t Dumper)
- Disposal of Pile Arisings (1297m3)
Main Site Works
- Excavate and Dispose 10k + m3 Inert Material (All inert Material to Roadstone)
- Basement Dig
- Attenuation Tanks
- Foundations
- Lift Pits
- Cores
- Crane Bases
- Deepening’s
- Installation of Piling Matt (6500m2)
- Installation of Blinding
- Installation of 3500m3 Leanmix to underside of Foundion
- Installation of Drainage,
- Installation of all Basement level Drainage
- Installation of Podium Level Drainage
- Includes all Bedding & Surrounds & Backfilling as required
- Services & Ducting,
- Installation of all Services and Ducting (Below Ground)
- Include all Bedding & Surrounds & Backfilling as required
- Roads Paths & Pavement (Making up Levels only)
- Installation of Drainage,