Featured

The Frame

M&N scope of works included: Completion of demolition works on site to basement walls and floor slabs Importing of 500m3 of piling matt Pile attendance for the duration of piling works Installation of groundforce flying shores Bulk excavation and removal off site of 16,000m3 of material including 3,000m3 of contaminated Material. This project was undertaken […]

The Frame Read More »

Waterfront South Central

Waterfront South Central, which is being developed by Ronan Group Real Estate (RGRE), involves the construction of 3 no. commercial office buildings and will transform Dublin’s North Docklands. It will see the development of Citi’s new European bank headquarters. The nine-storey future home of Citi in Ireland will come complete with roof terraces overlooking the

Waterfront South Central Read More »

DUB 90

M&N scope of works: Site strip and removal off site of 20,000m3 spoil Excavation of structural pads and installation of concrete blinding Installation of all underground site infrastructure including service ducting and drainage – both foul and surface water M&N worked to a very time sensitive program on this project, as the duration from commencement

DUB 90 Read More »

Grey Abbey View

M&N were appointed by Glenveagh Homes Ltd as PSCS to carry out  the Earthworks and Civil Engineering works for Grey Abbey View in Kildare. The scope of works included: The establishment of the site compound and project offices including, wheel wash and weigh bridge facilitates, full time road sweeping on local roads, plant storage and

Grey Abbey View Read More »

Amgen

M&N undertook this intricate project within a live pharmaceutical plant, focusing on bulk excavation as part of the enabling works package. The excavated material was diligently managed, with disposal carried out offsite via trucks at various locations (IMS Naul, Ballynagran and Enva Portlaoise), each determined by material classification and agreed upon in advance with relevant

Amgen Read More »

Data Centre – DUB058

New Data Centre 24,000m2 building. Site strip and disposal of 70,000m3 greenfield inert to licensed tips. Substructures, Pad foundations & bulk filing leanmix. Deep line drainage 375-1200 dia pipes SW/FW ranging from 5m-8m deep. Rock breaking circa 15,000m3 for trenches. Temporary works. Connections to local park services. Providing New entrance onto existing park. Attenuation pond

Data Centre – DUB058 Read More »

Fibonacci Square

Facebook New International Headquarters. Two storey basement dig within secant piled wall 15.00m deep. Approx 135,000m3 excavated & disposed off site brownfield site within 28 week programme duration. M&N achieved on average 130 artic loads per day at height of project in busy City Centre environment. M&N disposed circa 30,000 tonnes contaminated material for export

Fibonacci Square Read More »

TC2 Cherrywood

Groundworks for 384 Apartments and single storey basement carpark. M&N works included bulk dig 35,000m3 of mostly inert soil and disposal off site. Piling attendances to piling contractor during Piling phase. Substructure works, breaking 600& 900 dia piles, blinding works, backfilling basement wall. Under slab drainage. FW/SW Drainage & Site services works. Working closely alongside

TC2 Cherrywood Read More »

ESB New HQ

New ESB Headquarters. Two Storey Basement dig 8.00m deep, approx 72,000m3 excavation brownfield site. M&N achieved on average over 100 artic loads per day during bulk dig. Rock breaking 24,000m3 & disposed off site. Complex dig due to obstructions in ground reinforced concrete which had to be broken out from existing building. Disposal 60,000 tonnes

ESB New HQ Read More »

Scroll to Top