Featured

Data Centre – DUB058

New Data Centre 24,000m2 building. Site strip and disposal of 70,000m3 greenfield inert to licensed tips. Substructures, Pad foundations & bulk filing leanmix. Deep line drainage 375-1200 dia pipes SW/FW ranging from 5m-8m deep. Rock breaking circa 15,000m3 for trenches. Temporary works. Connections to local park services. Providing New entrance onto existing park. Attenuation pond …

Data Centre – DUB058 Read More »

Spencer North

Development for Hotel/Apartments at Spencer North Dublin. Bulk Dig 25,000m3 brownfield site. Disposal of over 50,000 tonnes contaminated material for export to barges and licensed facilities in Ireland. M&N achieved over 100 artic loads per day at height of project. Piling attendance on Piling contractor and disposalof Pile arisings off site. Substructures – Blinding, Breaking …

Spencer North Read More »

Fibonacci Square

Facebook New International Headquarters. Two storey basement dig within secant piled wall 15.00m deep. Approx 135,000m3 excavated & disposed off site brownfield site within 28 week programme duration. M&N achieved on average 130 artic loads per day at height of project in busy City Centre environment. M&N disposed circa 30,000 tonnes contaminated material for export …

Fibonacci Square Read More »

TC2 Cherrywood

Groundworks for 384 Apartments and single storey basement carpark. M&N works included bulk dig 35,000m3 of mostly inert soil and disposal off site. Piling attendances to piling contractor during Piling phase. Substructure works, breaking 600& 900 dia piles, blinding works, backfilling basement wall. Under slab drainage. FW/SW Drainage & Site services works. Working closely alongside …

TC2 Cherrywood Read More »

Dun Si St Marnocks Bay

Site Development & Groundworks for 150 housing units Station Road Portmarnock. Works included site strip & disposal 65,000m3 Greenfield Inert off site. Substructures for houses and external works. Permeable paving to house driveways. Site Infrastructure works includes SW/FW drainage. Manholes installed using perfect base system by Tracey Concrete. Installation of foul pumping station. Construction for …

Dun Si St Marnocks Bay Read More »

ESB New HQ

New ESB Headquarters. Two Storey Basement dig 8.00m deep, approx 72,000m3 excavation brownfield site. M&N achieved on average over 100 artic loads per day during bulk dig. Rock breaking 24,000m3 & disposed off site. Complex dig due to obstructions in ground reinforced concrete which had to be broken out from existing building. Disposal 60,000 tonnes …

ESB New HQ Read More »

Charlemont Square

A mixed used development double storey basement dig 8.00m deep brownfield site. M&N excavated approx 130,000m3 material and disposed off site. Temporary works – M&N installed propping to perimeter basement. M&N achieved over 130 artic loads per day at height project. Substructure – Blinding works carried out. Sub slab drainage & In slab drainage works.

Chatham Court

New Office/Retail development. M&N excavated double storey basement 12.00m deep dig in a tight city centre site off Grafton street. Volume excavation was 12,000m3 all removed by Tipper trucks. M&N Site logistics team enabled all this material to be removed safely and efficiently through proper planning and coordination with relevant stakeholders. Spoil removed to licensed …

Chatham Court Read More »

Scroll to Top