Grey Abbey View
Site Development with Drainage,Utilities and Road construction
Demolition Works to include 7,000 sqft house & Basement Bulk Dig of 25,000m3
Installation of 3.2 km Foul Drainage line, Manholes & Associated Works
Site strip 15,000m3 Greenfield inert off site to licensed tip. Site development works carried out for 75 number residential units. Works included Foul/Storm drainage varying in depths from 2.00m – 6.00m deep Construction Attenuation tank, Storm/Foul connections. Site infrastructure roads & associated services. Project also included outside boundary works which included 200metres deep line foul …
Development of 150 Social Housing Units. Site strip & disposal 25,000m3 greenfield inert material. Site infrastructure works including roads, drainage, services, attenuation tank & connections to local services. Site curtilage and substructure works to housing units. Works all in accordance with local authority.
Site development & Groundworks for 330 units in Adamstown. Works included site strip & disposal 40,000m3 greenfield inert material on site. Rock breaking 3,000m3 for deep line storm/foul drainage 2.00-5.00m deep. Manholes installed using Perfect Base system by Tracey Concrete. Paving to housing units & public driveways.
Site Development & Groundworks for 150 housing units Station Road Portmarnock. Works included site strip & disposal 65,000m3 Greenfield Inert off site. Substructures for houses and external works. Permeable paving to house driveways. Site Infrastructure works includes SW/FW drainage. Manholes installed using perfect base system by Tracey Concrete. Installation of foul pumping station. Construction for …
New social housing development 50 number units. A fireworks factory once stood on this site which led to site contamination. M&N disposed circa 30,000 tonnes contaminated spoil off site. Works including Site strip 15,000m3 brownfield site, infrastructure works including roads, drainage, services & connections to local authority services outside site boundary. Substructure works, piling attendance. …
Development 90 social housing units for SDCC. Site strip excavation of 20,000m3 inert material disposed off site. Substructure works, strip foundations, floors in substructure all in accordance with local authority. Site Infrastructure works, access roads, main drainage, watermains, kerbing, footpaths. External works, drainage, services, landscaping, footpaths, paving. Connections to local services outside site boundary on …